Fund the work that comes before delivery

What a funder can cover before a team starts delivering a digital service.

A floor-plan sketch, notes and a measuring tape on a workshop table.

Say you take over a charity's work with two nurseries and a primary school. The partners want to help families prepare for reception, and there's a budget line for a new transition tool. Everyone has a slightly different account of where the problem starts. The school wants information sooner, the nurseries already send it twice, and some parents have been given dates they can't make. The person holding the budget needs to agree what the partnership can spend while it figures out which of those problems it can fix.

On 10 June the Department for Education told schools and early years providers in England that they could apply for funding to form partnerships to support children starting reception. The opportunity had been published the day before. The first phase, scheduled for September 2026 to March 2027, was for building partnerships, identifying local needs and beginning to plan the work. The department described funding for up to 100 partnerships across the initiative. June update for local authorities · Funding details and update history

A development budget can pay for the school to release a member of staff for half a day, even if the discussion leads to a different service from the one it first expected. Record what that time bought while the people who did the work can still explain it.

Pay for the decisions you need to make

For the hypothetical reception project, start with one transition and trace it through the real jobs people do. Ask a nursery to show what it sends, and ask the school what it can use when it arrives. Use a dummy record. A parent might be able to tell you that they receive three dates in three places, but they'd have little reason to know which system generated each one. The project needs time from both people who can show the work and people who have to deal with its consequences.

Put that staff time in the plan with the rest of the costs. Two hours of a nursery manager's time may involve arranging cover. Helping a family take part can mean paying for interpreting or arranging a conversation outside someone's shift. Name the decisions those sessions need to inform. A broad commitment to consultation in a budget can leave people wondering whether they can spend money on the one conversation they really need.

A modest trial can answer a question before a procurement starts. In this case the partners might agree a single set of dates for six hypothetical families and check how the school and nurseries would publish amendments. Then try it for an agreed, limited group with the service leads. If the existing methods can handle the change, the partners could spend more on explaining dates and less on software. If the dates keep diverging, the trial gives them a place to investigate. The staff time spent running it should be visible even if the software idea is dropped.

Give the next decision a record of its own

At a partnership meeting someone will agree to investigate a possibility, and a month later the notes will be read as if permission to buy it had been given. Keep the work under consideration in a record the budget holder can read. For a decision to proceed, record which partners agreed, the amount they authorised and what has to happen before a further commitment. If the terms need funder approval, record who is asking and when a reply is needed. You want the incoming finance lead to be able to tell if an invoice was expected.

Keep a short account of the alternatives the partners tried. In the reception example, the school may be able to change its dates in the ordinary system while one nursery can only send updates through a weekly bulletin. Record that alongside the decision on how to send amendments. If somebody can change the bulletin schedule later, the team will know which part of the decision to revisit, and it won't have to justify the entire project from memory.

Keep disagreements in the record when they affect a commitment. Suppose the nursery doesn't have cover to staff the test on the day the school suggested. Write down the condition and the person who can clear it. A shared plan with that sentence in it is more useful than minutes announcing unanimous support for a trial nobody can run. Keep household information in the systems agreed for the work. The grant decision needs the finding and the evidence behind it at an appropriate level, with private records accessible only where permission and purpose allow.

The partners also have to agree who looks after anything made in the trial. A temporary booking form, for example, may have an account, a public link and details about families that still need looking after once the test ends. Put an end date against it and agree who will handle any unfinished bookings. If the partnership wants to keep using the form through delivery, the person approving the next budget needs its recurring cost and a named partner willing to do the work. If the trial ends, someone should take the public link down and handle the records according to the agreement. Either decision has a cost and a person attached to it.

Close the phase while you still know how you spent it

Before putting in a proposal for delivery, review what the development phase bought. Read the budget beside the decision notes, and pick an expense whose value would be hard to explain from the invoice alone. In the example, a payment for cover at a nursery might have let the lead attend the meeting that identified the second, conflicting source of dates. Record that relationship while the people who know it are there. File the note where the person responsible for the next commitment can find it alongside the remaining budget.

The review needs enough room to stop a proposal. It could conclude that only two partners are ready, or that further expenditure depends on the school moving a deadline. Agree who can approve a smaller piece of work and what would trigger a fresh decision. Where a grant sets boundaries on changes, have someone check the terms with the funder before moving money or relying on a revised date.

The handover I would want from the development phase fits around the next commitment. It gives the delivery lead the current agreement, the person who can clear anything outstanding and evidence of the thing the partners have already tested. If the plan says the charity will run a new transition service on Monday mornings, the incoming lead needs to know who can open the room, where families get the date and which partner has budgeted the hours to answer when the first family rings.